Digital Enterprise Project (DEP)

The UC ANR Digital Enterprise Project is working to move away from fragmented "legacy" technologies to a single, integrated enterprise-grade platform that incorporates the following functions/tools:

  • Volunteer & Enrollment Management
  • Events Registration
  • External-Facing Learning Platform (ANR Online)

The Vision

Our goal is one platform, one identity. We want to eliminate the friction of multiple logins and disconnected systems. For our volunteers and participants, this means a seamless experience where they can use a single platform to engage with multiple statewide programs, easily register for events, and complete mandatory training. By unifying these tools, we'll improve efficiency for our staff and create a much more welcoming, friendly experience for our partners in the community.

How We Prepared

To ensure this platform meets our actual needs, UC ANR created a Task Force of 39 dedicated subject matter experts across our programs and units in 2025. Supported by KAI Partners, Inc., this group defined 391 specific requirements to ensure the new system supports our mission and our people.

This effort led us to Phase 2: the search for the right implementation partner. After a rigorous RFP process and in-person demonstrations, the feedback from evaluators across ANR was clear. Based on your peers' input, we've selected Deloitte to build our new platform on Microsoft Dynamics.

The Road Ahead

We are now entering Phase 3: the most exciting part of this multi-year journey: implementation. As shown in the timeline below, there is a lot of work happening behind the scenes to make this a reality.  

Filled cells indicate when each project phase is underway.

Digital Enterprise Project timeline from August 2026 through December 2027
Project PhaseFall 2026Winter 2027Spring 2027Summer 2027Fall
2027
Planning & DiscoveryUnderway    
Design, Configuration & IntegrationUnderwayUnderway   
Testing, Training & Migration  UnderwayUnderway 
Launch   Launch date: Aug. 30, 2027 
Post-Launch Support   UnderwayUnderway through Dec. 17, 2027

Project Timeline Summary:

The Digital Enterprise Project runs from August 2026 through December 2027.

Major phases include project initiation and planning, discovery and design, Canvas LMS setup, configuration and integration, testing, training and change enablement, production cutover, go-live, hypercare, and extended help desk support.

Key milestones:

  • Project Start (Aug. 31, 2026)
  • Canvas Minor Release UAT Complete (Dec. 11, 2026)
  • Build Complete (May 7, 2027)
  • Training Complete (July 2, 2027)
  • System Readiness Complete (July 30, 2027)
  • Volunteer System Freeze Period (Aug. 9–30, 2027)
  • Go-Live (Aug. 30, 2027)
  • Extended Support Complete (Dec. 17, 2027)

If you have any questions or would like to be more involved, please email ucanrdigital@ucanr.edu.