- Author: Pamela S Kan-Rice
Update 11/30/23: The cutover schedule has been revised and will now be Saturday, Dec. 9, from 6 a.m. to Monday, Dec. 11, concluding at 7 p.m.
ANR IT is excited to provide an update on our progress on relocating to a new Data Center and firing up new equipment. This project represents a significant step forward for ANR's IT infrastructure, bringing us closer to our objectives of modernizing our architecture, ensuring system stability, and ultimately enhancing the customer experience.
Minimizing impact on your work
As the project progresses in the next three weeks, our IT team is dedicated to minimizing disruptions to your work and ensuring clear communication. There will...
- Author: Pamela Kan-Rice
To ensure we continue to enhance our security posture, we will be moving our infrastructure behind a new Palo Alto Firewall.
During this maintenance window, UC ANR web services will be down and unavailable. This includes ucanr.edu, ArcCatalog, and all subdomains, i.e., website.ucanr.edu.
Planned maintenance activities will occur on Wednesday, May 3, from 7 to 8 a.m. While we anticipate the outage being shorter, we want to allocate an hour for the move.
Thank you in advance for your patience and support. If you have any questions, don't hesitate to get in touch with IT at